The project manager has just completed a business process improvement project. The project has been deemed a failure by management primarily because it was completed three weeks late. In the project charter, the sponsor imposed an admittedly aggressive deadline. The project manager claims the timeline was unrealistic from the start, and he and the team did everything possible to achieve the required timeline. An unrealistic schedule is the fault of the: A:Customer B:Project manager C:Sponsor D:Team 更多最新试题及解答请进入【象网】公众号或【象网PMP】小程序