You are working on the performance reporting for the project you are managing. Schedule performance is the top constraint. As you are gathering the data, you need information for the formulas that you will be reporting on. Which of the following represent

作者:admin  阅读量:3271  时间:1970-01-01
You are working on the performance reporting for the project you are managing. Schedule performance is the top constraint. As you are gathering the data, you need information for the formulas that you will be reporting on. Which of the following represents the value of work actually completed? A:Estimate to complete B:Earned value C:Planned value D:Actual cost 更多最新试题及解答请进入【象网】公众号或【象网PMP】小程序