The project has been going relatively well, although there have been some problems with resource availability and the project scope has changed more than was expected. The project is now completing one of its phases. Of all decisions, the sponsor must con

作者:admin  阅读量:1934  时间:1970-01-01
The project has been going relatively well, although there have been some problems with resource availability and the project scope has changed more than was expected. The project is now completing one of its phases. Of all decisions, the sponsor must consider during an end-of-phase review meeting, the most difficult is: A:Authorizing scope change for the next phase B:Decreasing scope to maintain the budget C:Authorizing budget increases for the next phase based on scope changes D:Cancelling the project 更多最新试题及解答请进入【象网】公众号或【象网PMP】小程序