A trend report was given to the project manager, who reacted to the report by investigating what activity or activities had not been done, but should have been done, to date. What did the report show?

作者:admin  阅读量:3123  时间:1970-01-01
A trend report was given to the project manager, who reacted to the report by investigating what activity or activities had not been done, but should have been done, to date. What did the report show? A:The budget at completion (BAC) was higher than planned. B:The cost performance index (CPI) was 0.8 and the schedule performance index (SPI) was 1.2. C:Actual cost was below planned and schedule progress was less than planned. D:The schedule performance index (SPI) was 1.3 and the estimate at completion (EAC) was greater than planned. 更多最新试题及解答请进入【象网】公众号或【象网PMP】小程序